Develop and install ten printer drives Budget= 100,000 Time= 10 weeks At week 5 a) 4 printer drives developed & installed b) 47,500. Spend to
Develop and install ten printer drives
Budget= 100,000
Time= 10 weeks
At week 5
a) 4 printer drives developed & installed
b) 47,500. Spend to date
Calculate- PV, AC, EV, SV, CV, SPI, CPI, EAC, ETC