. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis...
Fantastic news! We've Found the answer you've been seeking!
Question:
Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average days past due.
Using the FCFS first come, first served decision rule for sequencing the customers, the order is:
Using the EDD earliest due date decision rule for sequencing the customers, the order is to resolve a tie, use the order in which the jobs were received:
The average flow time and average days past due for each option are: Enter your responses rounded to one decimal place.