Question

1 Approved Answer

Develop the network diagram for the shoreline baseball stadium project using the details.Carryout the Forward an Backward passes. Ensure to show a proof of description

Develop the network diagram for the shoreline baseball stadium project using the details.Carryout the Forward an Backward passes. Ensure to show a proof of description of how you arrived at your figures on all the nodesIdentify the critical activitiesDetermine and state the critical paths

image text in transcribed
MGMT 640. Week 4 - Network Practice Exercise - Including Online Forum Participation Shoreline Baseball Stadium Project. ID Activity Duration Predecessor(s) 1 Clear stadium site 70 days 2 Demolish existing building 30 days 1 3 Set up construction site 70 days 2 4 Drive support piling 120 days 1 5 Pour lower concrete bowl 120 days 4 6 Pour main concourse 120 days 3,5 7 Install playing field 90 days 3,5 8 Construct upper steel bowl 120 days 3,5 9 Install seats 140 days 6,8 10 Build luxury boxes 90 days 6,8 11 Install jumbotron 30 days 6,8 12 Stadium infrastructure 120 days 6,8 13 Construct steel canopy 75 days 9 14 Light installation 30 days 13 15 Build roof supports 90 days 5 16 Construct roof 180 days 15 17 Install roof tracks 90 days 15 18 Install roof 90 days 16,17 19 Inspection 20 days 7,10,11,12,14,18 20 Cleanup 21 days 19

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Experiencing MIS

Authors: David Kroenke

2nd Edition

0136078680, 9780136078685

More Books

Students also viewed these General Management questions

Question

1. To understand how to set goals in a communication process

Answered: 1 week ago