Question
1 Approved Answer
Develop Work Center OH rates based on budgeted '23 expenses. Three sets of OH rates should be developed, one using the prior year's actual hours,
Develop Work Center OH rates based on budgeted '23 expenses. Three sets of OH rates should be developed, one using the prior year's actual hours, one using '23 budgeted hours, and one using practical capacity. |
FACT SET |
The company produces 12 items across 4 work centers. Individual items can only be produced in one work center. |
The "Work Center Data" tab shows relevant data related to the items they produce, which work centers they are produced in, and the rates at which they are run. |
The "Expense Data" tab shows selected expense accounts from the company's P&L. |
The company runs all work centers 5 days per week, 50 weeks per year. They run two 8-hour shifts per day. When performing any analyses using practical capacity per work center, they estimate 80% uptime. |
Direct Labor is incurred at the following split: WC 1 = 40%, WC 2 = 15%, WC 3 = 30%, WC 4 = 15% |
The plant manager supports all 4 work centers evenly. Finance and their supplies also are considered to support all 4 work centers evenly. |
Production Supplies are used in the work centers as follows: WC 1 = 30%, WC 2 = 25%, WC 3 = 35%, WC 4 = 10% |
Equipment maintenance is spread based on the estimated machine hours for the year in each work center. |
Fixed assets are assigned and tracked at the work center level. See the Other Data tab for further detail. |
The company has one OH rate per work center, based on machine hours. |
Rent is allocated based on square footage. See the Other Data tab for further detail. |
Round all calculations to the nearest dollar, EXCEPT for the OH rates. Round those to the nearest 2 decimal places. |
Work Center | Sq Ft | Asset # | Work Center | Acq Value | Years Prior | 22 Depr | 23 Depr | ||
1 | 75,000 | A1 | 1 | 200,000 | 6.5 | 14,286 | 0 | ||
2 | 60,000 | A2 | 1 | 50,000 | 6.5 | 3,572 | 0 | ||
3 | 80,000 | A3 | 1 | 125,000 | 6.5 | 8,929 | 0 | ||
4 | 105,000 | A4 | 2 | 100,000 | 3.5 | 14,286 | 14,286 | ||
A5 | 2 | 35,000 | 3.5 | 5,000 | 5,000 | ||||
A6 | 3 | 20,000 | 2.5 | 2,857 | 2,857 | ||||
A7 | 3 | 30,000 | 2.5 | 4,286 | 4,286 | ||||
A8 | 3 | 85,000 | 2.5 | 12,143 | 12,143 | ||||
A9 | 3 | 20,000 | 2.5 | 2,857 | 2,857 | ||||
A10 | 4 | 1,100,000 | 0.5 | 157,143 | 157,143 | ||||
A11 | 4 | 300,000 | 0.5 | 42,857 | 42,857 | ||||
A12 | 4 | 15,000 | 0.5 | 2,143 | 2,143 | ||||
Total Depr | 270,359 | 243,572 |
Step by Step Solution
★★★★★
3.45 Rating (161 Votes )
There are 3 Steps involved in it
Step: 1
Work Center OH Rates using prior years actual hours WC 1 2863 per hour WC ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started