Question
Developing a MRP - material requirements plan Below is needed to be completed. Please complete the tables for items C, D and E Each unit
Developing a MRP - material requirements plan
Below is needed to be completed.
Please complete the tables for items C, D and E
-
Each unit of A is composed of 1 unit of B, 2 units of C, 1 unit of D
-
C is composed of 2 units of D, 3 units of E
-
Items A, C, D, and E have on-hand inventories of 20, 10, 20, and 10 units, respectively
-
Item B has a scheduled receipt of 10 units in period 1
-
Item C has a scheduled receipt of 50 units in period 1
-
L4L is used for Items A and B
-
Item C requires a minimum lot size of 50 units
-
D and E are required to be purchased in multiples of 100 and 50, respectively
-
Lead times are one period for Items A, B, and C, and two periods for Items D and E
-
The gross requirements for A are 30 in period 2, 30 in period 5, and 40 in period 8
Period | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | ||
Item: A | Gross Requirements |
| 30 |
|
| 30 |
|
| 40 |
| |
| Scheduled receipts |
|
|
|
|
|
|
|
|
| |
LT= 1 | Projected on hand | 20 | 20 | 20 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Net requirements |
| 10 |
|
| 30 |
|
| 40 |
| |
Q= | Planned order receipts | 10 |
|
| 30 |
|
| 40 |
| ||
L4L | Planned order releases | 10 |
|
| 30 |
|
| 40 |
|
|
Period | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | ||
Item: B | Gross Requirements | 10 |
|
| 30 |
|
| 40 |
|
| |
| Scheduled receipts | 10 |
|
|
|
|
|
|
|
| |
LT= 1 | Projected on hand |
|
|
|
|
|
|
|
|
| |
| Net requirements | 0 | 0 | 0 | 30 | 0 | 0 | 40 |
|
| |
Q= | Planned order receipts |
|
| 30 |
|
| 40 |
|
| ||
L4L | Planned order releases |
|
| 30 |
|
| 40 |
|
|
|
Period | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | ||
Item: C | Gross Requirements | 20 |
|
| 60 |
|
| 80 |
|
| |
| Scheduled receipts | ||||||||||
LT= 1 | Projected on hand | ||||||||||
| Net requirements | ||||||||||
Q= | Planned order receipts | ||||||||||
min of 50 | Planned order releases |
Period | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | ||
Item: D | Gross Requirements |
| |||||||||
| Scheduled receipts |
| |||||||||
LT= 2 | Projected on hand |
| |||||||||
| Net requirements |
| |||||||||
Q= | Planned order receipts |
| |||||||||
multiples of 100 | Planned order releases |
|
Period | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | ||
Item: E | Gross Requirements | ||||||||||
| Scheduled receipts | ||||||||||
LT= 2 | Projected on hand | ||||||||||
| Net requirements | ||||||||||
Q= | Planned order receipts | ||||||||||
multiples of 50 | Planned order releases |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started