Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Dhahran Roads Hassan Malik, the financial manager of SADE, a Bahrain - based civil engineering company, reread the recently received fax. He was delighted that

Dhahran Roads
Hassan Malik, the financial manager of SADE, a Bahrain-based civil engineering company, reread the recently received fax. He was delighted that the nearly endless conversations with the Transportation Ministry of the municipality of Dhahran in eastern Saudi Arabia were finally coming to a close. SADE had been selected as the prime contractor for a 168 million Saudi riyal (SAR) project that involved the reconstruction and upgrading of the highway network linking the several terminals of the Dhahran airport and connecting the entire complex with the city. The Dhahran Roads project was indicative of projects on which SADE had established its international reputation for being a leading construction contractor. The total cost of the project was estimated to be SAR146 million, so the SAR168 million value provided only a 15% return, which was, unfortunately, below the 18% hurdle rate required by SADE for projects of this nature. On the other hand, the slightly less-than-desired return seemed a small cost to pay to maintain a steady flow of new projects during these slow economic times. The fax requested that Malik respond to the project proposal within a week. The wording of the contract would then be finalized in the subsequent weeks and the contract signed by mid-January 1993.
The Project The terms of the proposed contract contained several provisions:
At the signing of the contract, the ministry would advance to SADE 15% of the contracts total value.
If work progressed on schedule, SADE could bill the Ministry as milestones were reached in accordance with the following schedule:
1993 SAR 11 million
1994 SAR 36 million
1995 SAR 45 million
1996 SAR 43 million
1997 SAR 33 million
The Ministry would pay 80% of each bill received. Payment would, of course, be subject to a satisfactory inspection of the site by the Ministry. The 20% deduction would be withheld for (1) the recovery of the advance payment (15%) and (2) the accumulation of a retention fund (5%).
Half of the retention would be reimbursed at the time of completion (end of 1997). The second half would be repaid at the end of 1998, provided the roads did not show any flaws in their first year of use
During the past several months, the SADE engineering department had inspected the site, confirmed the surveys, and reviewed the drawings that had been provided by the Ministry. In the opinion of the vice-president of engineering, the project presented no unusual challenges. It was similar to several SADE projects in other countries that were now nearly complete and that had moved ahead without difficulty. For SADE to proceed, equipment would have to be ordered immediately so that it would be available in the fourth quarter of 1993 when earth moving would commence. The cost of the equipment would be SAR38 million. Seventy-five percent of the cost would have to be paid upon placement of the order; the balance was due on delivery. At the end of the project, the equipment would have no salvage value. The engineering department estimated that the cost of completing the project (not including the equipment) would be SAR108 million. SAR7 million would be expended in 1993 for preliminary site work. The project would then proceed with estimated costs of SAR25 million, SAR29 million, SAR27 million, and SAR20 million for the subsequent years. Preliminary discussions with several banks indicated that SADE would be able to raise SAR4 million in loans to help finance the project. The loans would carry a 12% annual interest (2% above prime, 5% above government securities) and would have to be repaid in full at the end of 1997. The project would be managed by one of SADEs experienced project managers, Harold Smithers. Smithers had just completed a major waterworks project in East Africa and was noted for strong engineering skills and tight fiscal control. Although the contract would be denominated in SAR, the foreign exchange exposure would be minimal since the Bahraini dinar was pegged to the SAR. In addition, Saudi Arabian and Bahraini tax laws would not require SADE to pay taxes on the profits of this contract.
1. Using the content of the case study, answer the following questions, and show your calculations clearly.
a) Prepare a cash flow analysis using the following template, and clearly show the hurdle rate & NPV
Start of 1993 End of 1993 End of 1994 End of 1995 End of 1996 End of 1997 End of 1998 Total
Total Receipts (add rows to specific sources)
Total Disbursements (add rows to show specific costs)
Net cash
b) Calculate the IRR for the project (3 points)
Hint: Most companies include the cost of debt in their MARR / hurdle rate recall the discussion around WACC (weighted average cost of capital) and its link to MARR / hurdle rate; you can assume that is also true for this case
c) What would be your recommendation to Malik? Should he say yes or no to the
opportunity? If yes, what fa

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Analysis And Use Of Financial Statements

Authors: Gerald I. White, Ashwinpaul C. Sondhi, Haim D. Fried

3rd Edition

0471375942, 978-0471375944

More Books

Students also viewed these Finance questions