Diamond Company makes one product and has set the following standards for materials and labor: Direct Materials Direct Labor Standard quantity or hours per unit
Diamond Company makes one product and has set the following standards for materials and labor:
Direct Materials Direct Labor
Standard quantity or hours per unit ? pounds 2.10hours
Standard price or rate ? per pound $8.50per hour
Standard cost per unit ? $17.85
During the past month, the company purchased 6,200 pounds of direct materials at a cost of $17,050. All of this material was used in the production of 1,300 units of product. Direct labor cost totaled $20,070 for the month. The following variances have been computed:
Materials quantity variance $1,200U
Total materials spending variance $350F
Labor efficiency variance $4,250F
Required:1.For direct materials:
a.Compute the standard price per pound for materials.(Do not round intermediate calculations. Round your answer to 2 decimal places.)
b.Compute the standard quantity allowed for materials for the month's production.
c.
Compute the standard quantity of materials allowed per unit of product.(Round your answer to 2 decimal places.)
2.For direct labor:
a.Compute the actual direct labor cost per hour for the month.
b.Compute the labor rate variance.(Input the amount as positive value. Do not round intermediate calculations. Indicate the effect of the variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance).)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started