Diana is conducting PERT analysis for a project network. She finds that the activities A, B, C, D, E, F, and G are on the

Diana is conducting PERT analysis for a project network. She finds that the activities A, B, C, D, E, F, and G are on the critical path. She also determines that the activities A, B, C, D, E, F, and G have standard deviations of 1, 2, 4, 2, 6, 2, and 4 days, respectively. Find the STANDARD DEVIATION of the critical path A-B-C-D-E-F-G.

Group of answer choices

21 days

4.58258 days

3 days

1.73205 days

9 days

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Research Methods

Authors: Alan Bryman, Emma Bell

3rd Edition

0199583404, 9780199583409

More Books

Students also viewed these General Management questions

Question

Technology

Answered: 1 week ago

Question

Population

Answered: 1 week ago

Question

The feeling of boredom.

Answered: 1 week ago