Dillon Products manufactures various machined parts to customer specifications. The company uses a job-order costing system and applies overhead cost to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,129,200 in manufacturing overhead cost at an activity level of 558,000 machine-hours. The company spent the entire month of January working on a large order for 12,700 custom-made machined parts. The company had no work in process at the beginning of January. Cost data felating to January follow: a. Raw materials purchased on account, $320,000. b. Raw materials used in production, $255,000 (80\% direct materials and 20% indirect materials). c. Labor cost accrued in the factory, $165,000 (one-third direct labor and two-thirds indirect labor). d. Depreciation recorded on factory equipment, $64,000. e. Other manufacturing overhead costs incurred on account, $85,500. f. Manufacturing overhead cost was applied to production on the basis of 40.620 machine-hours actually worked during the month. 9. The completed job for 12,700 custom-made machined parts was moved into the finished goods warehouse on January 31 to await delivery to the customer. (In computing the dollar amount for this entry, remember that the cost of a completed job consists of direct materials, direct labot, and appliod overhead.) Required: 1. Prepare joumal entries to record items (a) through (f) above (Ignore item ( 9 ) for the moment]. 2. Prepare T-accounts for Manufacturing Overhead and Work in Process. Post the relevant items from your journal entries to these Taccounts. 3. Prepore a joumal entry for item (a) above. 4. If 10,100 of the custom-made machined parts are shipped to the customer in February, how much of this job's cost will be included in cost of goods sold for February? Dillon Products manufectures various machined parts to customer specifications. The company uses a job-order costing system and opplies overhead cost to jobs on the basis of machine-hours. At the beginning of the year, the company used a cost formula to estimate that it would incur $4,129,200 in manufacturing overhead cost at an activity level of 558,000 machine-hours. The company spent the entire month of January working on a Large order for 12,700 custom-made machined parts. The comparny had no work in process ot the beginning of January. Cost data relating to January follow: a. Row materials purchased on account, $320,000. b. Raw materials used in production, $255,000(80% direct materials and 20% indirect materials). c. Labor cost accrued in the factory, $165,000 (one-third direct labor and two-thirds indirect labor). d. Depreciation recorded on factory equipment, $64,000. e. Other manufacturing overheod costs incurfed on account, $85,500. f. Manufacturing overhead cost was applied to production on the basis of 40,620 machine-hours actually worked during the month. 9. The completed job for 12,700 custom-made machined ports was moved into the finished goods warehouse on January 31 to await delivery to the customer. (In computing the dollar amount for this entry, remember that the cost of a completed job consists of direct materials. direct labor, and applied overhead.) Required: 1. Prepare journal entries to record items (a) through (f) above lignore item (g ) for the moment] 2. Prepare T-accounts for Manufacturing Overhead arid Work in Process; Post the relevant items from your journal entries to these T. accounts. 3. Prepare a joumal entry for item (g) above. 4 . If 10,100 of the custom-made machined parts are shipped to the customer in February, how much of this job's cast will be included in cost of goods sold foe February? Required: 1. Prepare journal entries to record items (a) through ( f ) above [ignore item ( g ) for the moment]. 2. Prepare T-accounts for Manufacturing Overhead and Work in Process. Post the relevant items from your journal entries to these Taccounts. 3. Prepare a journal entry for item (g) above. 4. If 10,100 of the custom-made machined parts are shipped to the customer in February, how much of this job's cost will be included in cost of goods sold for February? (3) Answer is complete but not entirely correct. Complete the question by entering your answers in the tabs below. If 10,100 of the custom-made machined parts are shipped to the customer in February, how much of this job's cost will be included in cost of goods sold for February? (Round your intermediate calculations to 2 decimal places and final answer to the nearest whole dollar amount.)