Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Direct Labor Budget Duran Company produces asphalt roofing materials. The production budget in bundles for Duran's most popular weight of asphalt shingle is shown for
Direct Labor Budget
Duran Company produces asphalt roofing materials. The production budget in bundles for Duran's most popular weight of asphalt shingle is shown for the following months:
Month | Units |
---|---|
March | 9,000 |
April | 13,000 |
May | 14,400 |
June | 17,000 |
Each bundle produced requires (on average) 0.30 direct labor hours. The average cost of direct labor is $20 per hour.
Required:
Prepare a direct labor budget for March, April, and May, showing the hours needed and the direct labor cost for each month and in total. Do not include a multiplication symbol as part of your answer.
Duran Company | ||||
---|---|---|---|---|
Direct Labor Budget | ||||
For March, April, and May | ||||
Line Item Description | March | April | May | Total |
Units to be produced | ______ | ______ | ______ | ______ |
Direct labor time per unit (hours) | ______ | ______ | ______ | ______ |
Total hours needed | ______ | ______ | ______ | ______ |
Cost per hour | $______ | $______ | $______ | $______ |
Total direct labor cost | $______ | $______ | $______ | $______ |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started