Question
Direct labor cost budget Rip Court Racket Company manufactures two types of tennis rackets, the Junior and Pro Striker models. The production budget for March
Direct labor cost budget
Rip Court Racket Company manufactures two types of tennis rackets, the Junior and Pro Striker models. The production budget for March for the two rackets is as follows:
Junior | Pro Striker | |
Production budget | 4,400 units | 11,300 units |
Both rackets are produced in two departments, Forming and Assembly. The direct labor hours required for each racket are estimated as follows:
Forming Department | Assembly Department | |
Junior | 0.10 hour per unit | 0.20 hour per unit |
Pro Striker | 0.15 hour per unit | 0.35 hour per unit |
The direct labor rate for each department is as follows:
Forming Department | $15 per hour |
Assembly Department | $8 per hour |
This information has been collected in the Microsoft Excel Online file. Open the spreadsheet, perform the required analysis, and input your answers in the question below.
Open spreadsheet
Prepare the direct labor cost budget for March.
Rip Court Racket Company | ||
Direct Labor Cost Budget | ||
For the Month Ending March 31 | ||
Forming Department | Assembly Department | |
Hours required for production: | ||
Junior | fill in the blank 2 | fill in the blank 3 |
Pro Striker | fill in the blank 4 | fill in the blank 5 |
Total hours required | fill in the blank 6 | fill in the blank 7 |
Hourly rate | x $fill in the blank 8 | x $fill in the blank 9 |
Total direct labor cost | $fill in the blank 10 | $fill in the blank 11 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started