Question

1 Approved Answer

Direct Materials, Direct Labor, and Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical into plastic. Standard costs and actual costs for direct

Direct Materials, Direct Labor, and Factory Overhead Cost Variance Analysis

Mackinaw Inc. processes a base chemical into plastic. Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 4,400 units of product were as follows:

Standard Costs Actual Costs
Direct materials 5,700 lb. at $4.90 5,600 lb. at $4.70
Direct labor 1,100 hrs. at $16.40 1,130 hrs. at $16.60
Factory overhead Rates per direct labor hr.,
based on 100% of normal
capacity of 1,150 direct
labor hrs.:
Variable cost, $4.50 $4,900 variable cost
Fixed cost, $7.10 $8,165 fixed cost

Each unit requires 0.25 hour of direct labor.

Required:

a. Determine the direct materials price variance, direct materials quantity variance, and total direct materials cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Direct materials price variance $fill in the blank 1

FavorableUnfavorableFavorable

Direct materials quantity variance fill in the blank 3

FavorableUnfavorableFavorable

Total direct materials cost variance $fill in the blank 5

FavorableUnfavorableFavorable

b. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Direct labor rate variance $fill in the blank 7

FavorableUnfavorable

Direct labor time variance fill in the blank 9

FavorableUnfavorable

Total direct labor cost variance $fill in the blank 11

FavorableUnfavorable

c. Determine variable factory overhead controllable variance, the fixed factory overhead volume variance, and total factory overhead cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Variable factory overhead controllable variance $fill in the blank 13

FavorableUnfavorable

Fixed factory overhead volume variance fill in the blank 15

FavorableUnfavorable

Total factory overhead cost variance $fill in the blank 17

FavorableUnfavorable

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding And Conducting Information Systems Auditing

Authors: Arif Ahmed, Veena Hingarh

1st Edition

1118343743, 978-1118343746

More Books

Students also viewed these Accounting questions

Question

=+20.12. If F(x-) Answered: 1 week ago

Answered: 1 week ago