Question

1 Approved Answer

Direct Materials Purchases Budget: Direct Labor Budget Crescent Company produces stuffed toy animals; one of these is Arabeau the Cow. Each Arabeau takes 0.20 yard

Direct Materials Purchases Budget: Direct Labor Budget

Crescent Company produces stuffed toy animals; one of these is Arabeau the Cow. Each Arabeau takes 0.20 yard of fabric (white with irregular black splotches) and eight ounces of polyfiberfill. Fabric costs $3.50 per yard and polyfiberfill is $0.05 per ounce. Crescent has budgeted production of Arabeaus for the next four months as follows:

Units
October 42,000
November 90,000
December 50,000
January 40,000

Inventory policy requires that sufficient fabric be in ending monthly inventory to satisfy 20 percent of the following months production needs and sufficient polyfiberfill be in inventory to satisfy 40 percent of the following months production needs. Inventory of fabric and polyfiberfill at the beginning of October equals exactly the amount needed to satisfy the inventory policy.

Each Arabeau produced requires (on average) 0.10 direct labor hour. The average cost of direct labor is $15 per hour.

Required:

1. Prepare a direct materials purchases budget of fabric for the last quarter of the year showing purchases in units and in dollars for each month and for the quarter in total. Round your answers to the nearest cent, if required.

Crescent Company
Direct Materials Purchases Budget for Fabric
For the Fourth Quarter
October November December Total
Units produced
DM per unit (yd.)
Production needs
Desired ending inventory (yd.)
Total needed
Less: Beginning inventory
DM to be purchased (yd.)
Cost per yard $ $ $ $
Total purchase cost $ $ $ $

Feedback

The purchases amount can be determined by considering beginning and ending (desired) inventory amounts. Also, consider expected usage.

2. Prepare a direct materials purchases budget of polyfiberfill for the last quarter of the year showing purchases in units and in dollars for each month and for the quarter in total. Round your answers to the nearest cent, if required.

Crescent Company
Direct Materials Purchases Budget for Polyfiberfill
For the Fourth Quarter
October November December Total
Units produced
DM per unit (oz.)
Production needs
Desired ending inventory (oz.)
Total needed
Less: Beginning inventory
DM to be purchased (oz.)
Cost per ounce $ $ $ $
Total purchase cost $ $ $ $

Feedback

See Cornerstone 8.3

3. Prepare a direct labor budget for the last quarter of the year showing the hours needed and the direct labor cost for each month and for the quarter in total. Round your answers to the nearest cent, if required.

Crescent Company
Direct Labor Budget
For the Fourth Quarter
October November December Total
Units produced
Direct labor time per unit (hours)
Direct labor hours needed
Cost per direct labor hour $ $ $ $
Total direct labor cost $ $ $ $

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting

Authors: Robert Libby, Patricia Libby, Daniel Short

5th Edition

0073208140, 978-0073208145

More Books

Students also viewed these Accounting questions

Question

Can knowledge workers and/or professionals be performance-managed?

Answered: 1 week ago

Question

Does a PMS enhance strategic integration within HRM?

Answered: 1 week ago