Directions: Answer the following questions and be sure to provide your screen shots or your full notes with calculations for full credit. QM for Windows
Directions: Answer the following questions and be sure to provide your screen shots or your full notes with calculations for full credit. QM for Windows is a fine tool to complete these problems. In addition, it is expected that the answers to these problems will be provided in a professional and masters level manner. Lastly, this is an individual assignment not a group assignment. It is expected that each student would complete the assignment individually.
Problem #1
PERT Analysis: The following represents a project with known activity times. All times are in weeks.
Activity | Immediate Predecessor | Time |
A | - | 5 |
B | - | 4 |
C | A | 3 |
D | B | 7 |
E | C, D | 4 |
F | B | 6 |
Using the data in the above table,
What is the minimum possible time required for completing the project?
What is the critical path?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started