Use the accompanying template to help complete the following exercises and provide a comprehensive narrative to support your findings: 1. In month 9 the following

Use the accompanying template to help complete the following exercises and provide a comprehensive narrative to support your findings:

1. In month 9 the following Project Stallion information is available: Actual cost is $2,000, earned value is $2,100, and planned cost is $2,400. Compute the SV and CV for the project. What is your assessment of the project on month 9?

2. On day 51 Project Blue has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV and CV for the project. What is your assessment of the project on day 51?

Task Cumulative Totals % Complete EV AC PV CV SV 

  

Task Cumulative Totals % Complete EV AC PV CV SV

Step by Step Solution

3.38 Rating (157 Votes )

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Horngrens Accounting

Authors: Tracie L. Miller Nobles, Brenda L. Mattison, Ella Mae Matsumura, Carol A. Meissner, Jo Ann L. Johnston, Peter R. Norwood

10th Canadian edition Volume 1

978-0134213101, 134213106, 133855376, 978-0133855371

More Books

Students also viewed these Accounting questions

Question

Show that [see (8. 39)]. av. var () 1 TIZ t-1 Exa

Answered: 1 week ago