Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Discussion Scenario: Review the following case. IN RE RIDDLE 444 B.R. 681 (Bankr. N.D. Ga. 2011) OPINION: PAUL W. BONAPFEL, Bankruptcy Judge. Northside Bank (the

Discussion Scenario: Review the following case.

IN RE RIDDLE

444 B.R. 681 (Bankr. N.D. Ga. 2011)

OPINION: PAUL W. BONAPFEL, Bankruptcy Judge.

Northside Bank (the "Bank") has rejected the Chapter 11 Plan filed by Green Hobson Riddle, Jr., and objected to its confirmation. At the hearing on confirmation, the Court determined that the Plan meets all requirements for confirmation in 11 U.S.C. 1129(a) except the requirement in 1129(a) (8) that all classes of impaired claims accept it, a requirement that the Debtor cannot meet in view of the Bank's rejection of the Plan as the sole member in its class. The question considered here is whether the plan is confirmable under the so-called "cram-down" provision, 11 U.S.C. 1129(b), notwithstanding the Bank's failure to accept it.

POSITIONS OF THE PARTIES

The Bank is the holder of a claim in the amount of approximately $907,000 secured by a first priority deed to secure debt on approximately 36 acres of real property generally referred to as the "Highway 411/Dodd Blvd Property" and a second priority deed to secure debt on a condominium unit generally referred to as the "Heritage Square Property." The Bank also holds a judgment lien.

The Plan proposes to surrender the Highway 411/Dodd Blvd Property, which the Plan asserts is worth $1.2 million, to the Bank by execution of a quitclaim deed to the Bank upon confirmation in full satisfaction of the Bank's claim, thereby requiring cancellation of both the second priority security deed on the Heritage Square Property and the judgment lien.

The Bank rejected the Plan and appeared at the confirmation hearing to object to its confirmation because all classes of impaired claims had not accepted it as 11 U.S.C. 1129(a)(8) requires. As secured creditors typically are, the Bank is the sole member of its class so its vote determines the vote of that class. At that hearing, the Court determined that the Plan meets all requirements for confirmation set forth in 1129(a), except the requirement of paragraph 8.

The Debtor requests that the Court confirm the plan pursuant to 11 U.S.C. 1129(b). Section 1129(b) is the so-called "cram-down" provision of Chapter 11 that permits confirmation notwithstanding the absence of acceptance by an impaired class if the treatment of the impaired, nonaccepting class "does not discriminate unfairly" and is "fair and equitable." With regard to a class of secured claims, like the Bank's, section 1129(b)(2) (A) requires that the plan meet one of three alternative conditions to be "fair and equitable." The Debtor invokes clause (iii) of 1129(b)(2)(A), which states that a plan is "fair and equitable" with regard to a class of secured claims if it provides for the secured creditor to realize the "indubitable equivalent" of its claim.

The Bank asserts that the plan does not satisfy the requirements of 1129(b) because it discriminates unfairly and because it does not provide for it to realize the "indubitable equivalent" of its claim.

SUMMARY OF FINDINGS OF FACT

The Court heard evidence at the hearing on January 27, 2011, with regard to the 1129(b)(2)(B) issues and announced its findings of fact on the record. In summary, the Court found that, properly marketed, the Highway 411/Dodd Blvd Property would likely sell for a price in the range of $1.2 million to $1.3 million, possibly more; that it would bring $990,000 at a "fire sale," i.e., a sale under distressed circumstances in which the seller is under pressure to sell promptly; that selling costs would be approximately $50,000; and that, consequently, the net proceeds realizable from a "fire sale" of the property would be $940,000. To determine what the Bank could realize from the property, it is necessary to deduct unpaid ad valorem taxes that have priority over the Bank's deed to secure debt. The parties agree that the amount of unpaid ad valorem taxes is $8,981.04.

The net amount realizable from the Heritage Square Property, after satisfaction of the first priority deed to secure debt that another lender holds, is at least $100,000. The Debtor testified that release of the Bank's second priority deed to secure debt on the Heritage Square Property is necessary to permit the Debtor to use that property as collateral for additional financing for one of his companies, which, in turn, is essential to the feasibility of the Plan and his ability to pay other claims as the Plan proposes.

DISCUSSION

Section 1129(b)(1) permits confirmation of a plan over the objection of a class of creditors if the plan does not "discriminate unfairly" and is "fair and equitable" with regard to the objecting class. Section 1129(b)(2)(A) lists three alternative ways that a plan may treat a secured claim to meet the "fair and equitable" requirement. Applicable here is the third alternative, 1129(b)(2)(A)(iii), which provides that a plan is fair and equitable if it provides for the secured creditor to realize the "indubitable equivalent" of its claim.

The provision for treatment of the Bank's claim is a so-called "dirt for debt" provision that seeks to satisfy a creditor's claim to the extent of the value of real estate that the lender holds as collateral. Such a provision may, under appropriate circumstances, provide the indubitable equivalent of the lender's claim. (Citations omitted.) The Plan here goes beyond the concept of transferring all of a lender's collateral to it in satisfaction of its secured claim. Rather, the Plan provides for the Bank to receive only part of its collateral, the Highway 411/Dodd Blvd Property, and to lose the additional collateral it has. The theory underlying the Debtor's ability to do so is that the Bank's receipt of the Highway 411/Dodd Blvd Property provides it with enough value to satisfy its claim in full, resulting in release of other collateral that the Bank holds as additional collateral for its claim.

In order for treatment of a secured creditor's claim to qualify as being the "indubitable equivalent" of the claim, the treatment must be completely compensatory. (Citations omitted.) In this regard, an equivalent is "indubitable" if no reasonable doubt exists that the creditor will be paid in full. (Citations omitted.) When the plan proposes the transfer of some, but not all, of the collateral to the creditor in full satisfaction of the debt, the court must take a conservative approach to valuation of the collateral in order to protect the secured creditor. (Citation omitted.)

Applying these standards here, the Court concludes that the transfer of the Highway 411/Dodd Blvd Property to the Bank provides for the realization of the indubitable equivalent of its claim. Specifically, the credible and uncontroverted evidence before the Court establishes that $990,000 is a "fire sale" value. In this regard, the "fire sale" value reflects a discount of at least $200,000 from what the property could be sold for if it were marketed in the usual way that such properties are marketed. The "fire sale" value of $990,000, then, clearly reflects a conservative approach to valuation that is the bare minimum that the property will sell for in a reasonably prompt time.

After payment of estimated selling expenses of $50,000 and satisfaction of unpaid ad valorem taxes of approximately $9,000, the remaining proceeds from such a "fire sale" would be $931,000, which is enough for the Bank to receive more than the amount now due (approximately $907,000), plus six months of interest (approximately $21,500 for 180 days at the per diem rate of $119) (a total of $928,500).

Based on the evidence before the Court, as reflected in its findings of fact, the Court concludes that no reasonable doubt exists that the transfer of the Highway 411/Dodd Blvd Property to the Bank will result in full payment of its claim. As such, the transfer provides for the realization by the Bank of the indubitable equivalent of its claim. The Plan therefore meets the "fair and equitable" requirement of 1129(b)(2)(A)(iii).

The Bank also contends that the plan discriminates unfairly because its claim is the only one that is being satisfied by the transfer of collateral. Section 1129(b)(1) requires that a plan "not discriminate unfairly" as a condition for its confirmation over its rejection by an impaired class.

This condition has little, if any, significance in the context of a secured claim. Because each secured creditor has collateral, repayment terms, and other rights that are unique to it, proper classification in a Chapter 11 plan requires a separate class for each secured claim. The propriety of the treatment of a secured claim is not generally determined by reference to the treatment of other secured claims. Nothing requires that a plan provide treatment for every secured claim with the same maturity date, rate of interest, payment schedule, or any other term. So a secured creditor must show something other than the uniqueness of its treatment to establish unfair discrimination. In any event, a provision that provides treatment for a secured creditor that provides the indubitable equivalent of its claimin this case, payment in fullcannot be said to be "unfair."

At the same time, it is important to recognize that 1129(b), the "cramdown" subsection, "provides only a minimum requirement for confirmation...so a court may decide that a plan is not fair and equitable even if it is in technical compliance with the Code's requirements." E.g., Atlanta Southern Business Park, 173 B.R. at 448. In this regard, it could be inequitable to conclude that a plan provision such as the one under consideration here is "fair and equitable," if the provision serves no reorganization purpose. See Freymiller Trucking, 190 B.R. at 916. But in this case, the evidence shows that elimination of the Bank's lien on other collateral is necessary for the reorganization of the Debtor and his ability to deal with all of the claims of other creditors who have accepted the Plan. No evidence demonstrates that the Plan is inequitable or unfair.

CONCLUSIONS OF LAW

Based on the findings of fact announced by the Court at the hearings in this case and the undisputed facts that the parties have agreed on, the Court concludes that the Plan's provisions with regard to treatment of the Bank's claim provide for the Bank to realize the indubitable equivalent of its claim, that the Plan does not unfairly discriminate with regard to the Bank's claim, and that the Plan's provisions with regard to the Bank's claim are fair and equitable. Consequently, the Court concludes that the Plan meets the requirements of 11 U.S.C. 1129(b) with regard to the Bank's claim such that its acceptance of the Plan is not required.

The Court having determined at the hearings that the Plan meets all other requirements for confirmation, the Court will enter a separate Order for confirmation of the Plan.

Topic Questions:

  1. Be sure you understand and can articulate how the claim of Bank in In re Riddle was impaired by the debtor's proposed plan. As of the date the petition was filed, how much was Bank owed by the debtor? Bank as of that time was secured by two consensual liens and one nonconsensual lien. What were they? What did the debtor's plan propose as to each of the two consensual liens and as to the nonconsensual lien? Did the plan propose to surrender all the property in which Bank held a security interest to Bank?
  2. Riddle interprets the indubitable equivalent language of 1129(b)(2)(A)(iii) to require proof "beyond a reasonable doubt" that the value offered the secured creditor in the debtor's plan will pay the creditor's secured claim in full. Many courts use a "clear and convincing" standard for indubitable value. Determine if the courts of your federal district or circuit have decided an indubitable value case and see what standard of proof for indubitable value is used.
  3. How did the court in Riddle calculate the net value of the property to be surrendered to Bank as proposed in the plan? How did it conclude that the net value would actually exceed the value of the Bank's secured claim and provide it with a windfall? Did it consider both a likely nondistress and distress sale value of the property being considered? Did it deduct likely expenses associated with the property and sale of the property in its calculations?
  4. Assume an appraiser for debtor testified as is summarized in the Summary of Findings of Fact in the opinion but an appraiser for Bank had testified that the real estate market in the area was "beginning to stall" and that the property "normally" would bring $1.2 to $1.3 million and be on the market six to 12 months, but in the current market "might" bring as little as $1 million and be on the market six to 18 months, and in a fire sale where it was disposed of as quickly as possible "might" bring as little as $925,000. You are the judge. What impact will the qualifications and experience of the two opposing appraisers have on your decision regarding indubitable value? What difference will the standard of proof for indubitable value used in your district make?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Entrepreneurship

Authors: Andrew Zacharakis, William D Bygrave

5th Edition

1119563097, 9781119563099

Students also viewed these Law questions