Question
1 Approved Answer
Do It! Review 24-2 x Your answer is incorrect. Try again In Pargo Company's flexible budget graph, the fixed cost line and the total budgeted
Do It! Review 24-2 x Your answer is incorrect. Try again In Pargo Company's flexible budget graph, the fixed cost line and the total budgeted cost line intersect the vertical axis at $94,200. The total budgeted cost line is $366,980 at an activity level of 59,300 direct labor hours. Compute total budgeted costs at 75,000 direct labor hours. Total budgeted costs 366980
Step by Step Solution
There are 3 Steps involved in it
Step: 1