Dobson Construction specializes in the construction of commercial and industrial buildings. The contractor is experienced in bidding long-term construction projects of this type, with the

Dobson Construction specializes in the construction of commercial and industrial buildings. The contractor is experienced in bidding long-term construction projects of this type, with the typical project lasting fifteen to twenty-four months. The contractor uses the percentage-of-completion method of revenue recognition since, given the characteristics of the contractor's business and contracts, it is the most appropriate method. Progress toward completion is measured on a cost-to-cost basis. Dobson began work on a lump-sum contract at the beginning of 2015. As bid, the statistics were as follows:

Lump-sum price (contract price) $4,000,000

Estimated costs

Labor $ 850,000

Materials and subcontractor 1,750,000

Indirect costs 400,000 3,000,000

$1,000,000

At the end of the first year, the following was the status of the contract:

Billings to date $2,250,000

Costs incurred to date

Labor $ 464,000

Materials and subcontractor 648,000

Indirect costs 193,000 1,305,000

Latest forecast total cost 3,000,000

It should be noted that included in the above costs incurred to date were standard electrical and mechanical materials stored on the job site, but not yet installed, costing $105,000. These costs should not be considered in the costs incurred to date.

Instructions

(a) Indicate the amount of gross profit that would be reported on this contract at the end of 2015.

(b) Make the journal entry to record the income (loss) for 2015 on Dobson's books.

(c) Indicate the account(s) and the amount(s) that would be shown on the balance sheet of Dobson Construction at the end of 2015 related to its construction accounts. Also indicate where these items would be classified on the balance sheet. Billings collected during the year amounted to $1,900,000.

(d) Assume the latest forecast on total costs at the end of 2015 was $4,060,000. How much income (loss) would Dobson report for the year 2015?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Information Systems The Processes and Controls

Authors: Leslie Turner, Andrea Weickgenannt

2nd edition

9781118473030, 1118162307, 1118473035, 978-1118162309

More Books

Students also viewed these Accounting questions

Question

How can you defend against SQL injection attacks?

Answered: 1 week ago