Don Basmati, Earned Value Management Analyst, for the Lightweight Assault Reconnaissance (LAR) Program Support Team (PST) is preparing for his analysis. Functional Specialists have reported

Don Basmati, Earned Value Management Analyst, for the Lightweight Assault Reconnaissance (LAR) Program Support Team (PST) is preparing for his analysis. Functional Specialists have reported the following High Risks and Significant Issues RIO: Risk A (WBS 1.1.4): Identified as an Increda Corp. software risk highly likely to happen and if not properly mitigated could result in a 5-month slip and possibly affect a major milestone deliverable. Issue (WB 1.1.3): Increda Corp. and the PMO identified a $5.34M cost overrun. DCMA estimates the overrun to be $9.6M on additional surveillance data. What will Don do for cost and schedule based on this functional information? Please select from on of the following:

a) Subtract $4.26 to the Estimate at Completion and during schedule analysis incorporate the 5 month schedule slip that could adjust ECD

b) Add $2.7M to the Estimate at Completion and during schedule analysis and adjust the ECD by 5 months.

c) Add $9.6M to the Estimate at Completion and during schedule analysis and adjust ECD by 3 months.

d) Add $4.26M to the Estimate at Completion and during

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Effective Project Management Traditional Agile Extreme

Authors: Robert K. Wysocki

7th Edition

1118729161, 978-1118729168

More Books

Students also viewed these General Management questions