Donna Company would like to estimate the variable and fixed components of its maintenance costs and has compiled the following data for the last five
Donna Company would like to estimate the variable and fixed components of its maintenance costs and has compiled the following data for the last five months of operations:
Labor Hours Maintenance Cost
January 190 P677
February 120 P593
March 170 P646
April 110 P623
May 100 P582
Required:
[a] Using the high-low method of analysis, how much is the estimated variable cost per labor hour for maintenance?
[b] Using the high-low method of analysis, how much is the estimated total fixed cost per month?
[c] Using high-low, compute for the expected maintenance cost for June if expected labor hours is 150 hours.
[d] Using the least-squares regression method, how much is the estimated variable cost per labor hour for maintenance?
[e] Using the least-squares regression method, how much is the estimated total fixed cost per month for maintenance?
[f] Using the least-squares regression method, compute for the expected maintenance cost for June if expected labor hours is 150 hours.
[g] Using the least-squares regression equation, where is the total maintenance cost for March located with respect to the regression line?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Donna Company Maintenance Cost Analysis HighLow Method HL a Variable Cost per Hour Identify the highest and lowest activity levels labor hours Highest ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started