dont know whats wrong. following tasks are to be performed on an aseembly line The following tasks are to be performed on an assembly line:

dont know whats wrong. following tasks are to be performed on an aseembly line

image text in transcribed

The following tasks are to be performed on an assembly line: The workday is 9.5 hours long. Demand for completed product is 900 per day. a. Find the cycle time required to meet the desired output rate. (Round your answer to 1 decimal place.) b. What is the theoretical number of workstations required to meet the desired output rate? (Round up your answer to the next whole number.) d. Balance the line using sequential restrictions and the longest-operating-time rule. (Leave no cells blank - be certain to enter " 0 " wherever required. Round your answers to 1 decimal place.) e. What is the efficiency of the line balanced as in part (d) assuming it is running at the cycle time determined in part (a)? (Round your answer to 1 decimal place.) f. Suppose that demand rose from 900 to 1,150 units per day. What would you do? (Round your answer for cycle time down to the nearest whole number.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management Concepts

Authors: Frank Rothaermel

2nd edition

77645065, 1259384071, 9780077645069, 978-1259384073

More Books

Students also viewed these General Management questions