Draw a network diagram using the Two Pass method to answer the following questions: Activity Estimated time Successor A 4 B, C B 5 E
Draw a network diagram using the Two Pass method to answer the following questions:
Activity | Estimated time | Successor |
A | 4 | B, C |
B | 5 | E |
C | 6 | D |
D | 3 | E |
E | 10 | F, G |
F | 3 | H |
G | 6 | I |
H | 2 | I |
I | 3 | N/A |
What is the critical path?
What is the duration of the project?
Which tasks have total float? Which tasks have free float?