Draw a network diagram using the Two Pass method to answer the following questions: Activity Estimated time Successor A 4 B, C B 5 E

Draw a network diagram using the Two Pass method to answer the following questions:

Activity

Estimated time

Successor

A

4

B, C

B

5

E

C

6

D

D

3

E

E

10

F, G

F

3

H

G

6

I

H

2

I

I

3

N/A

What is the critical path?

What is the duration of the project?

Which tasks have total float? Which tasks have free float?

Which tasks can you crash in order to complete the project faster?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Information Modeling And Relational Databases

Authors: Terry Halpin, Tony Morgan

2nd Edition

0123735688, 978-0123735683

More Books

Students also viewed these Databases questions

Question

Write Hund's rule?

Answered: 1 week ago