Question

1 Approved Answer

Draw an Activity-on-Arrow diagram using the following task information. Any other type of diagram will receive a zero. The task names have been shortened to

Draw an Activity-on-Arrow diagram using the following task information. Any other type of diagram will receive a zero. The task names have been shortened to just letters. You may use any tool you like to draw the diagram. Calculate the slack for each task and label the critical path. 10 points for diagram and 10 points for correct slack calculations.

Task A, no dependency, 5 days

Task B, no dependency, 2 days

Task C, no dependency, 7 days

Task D, depends on Task A, 4 days

Task E, depends on Task B and Tack C, 11 days

Task F, depends on Tack C, 6 days

Task G, depends on Task D and Task E, 5 days

Task H, depends on Task E, 2 days

Task I, depends on Task E and Task F, 4 days

Task J, depends on Task H and Task I, 3 days

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic management concepts

Authors: Fred david

13th Edition

9780136120988, 136120997, 136120989, 978-0136120995

More Books

Students also viewed these General Management questions