Question
Draw an Activity-on-Arrow diagram using the following task information. Any other type of diagram will receive a zero. The task names have been shortened to
Draw an Activity-on-Arrow diagram using the following task information. Any other type of diagram will receive a zero. The task names have been shortened to just letters. You may use any tool you like to draw the diagram. Calculate the slack for each task and label the critical path. 10 points for diagram and 10 points for correct slack calculations.
Task A, no dependency, 5 days
Task B, no dependency, 2 days
Task C, no dependency, 7 days
Task D, depends on Task A, 4 days
Task E, depends on Task B and Tack C, 11 days
Task F, depends on Tack C, 6 days
Task G, depends on Task D and Task E, 5 days
Task H, depends on Task E, 2 days
Task I, depends on Task E and Task F, 4 days
Task J, depends on Task H and Task I, 3 days
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started