Question

1 Approved Answer

Draw an AOA network diagram representing the project. Use the technique of forward and backward pass and find the slack and float of each activity.

Draw an AOA network diagram representing the project. Use the technique of forward and backward pass and find the slack and float of each activity. Also find the critical path for this project and what is the shortest possible time needed to complete this project?

Activity Initial Node Final Node Estimated Duration 1 10 B 1 3. 12 1 4. D 2 3 4 3 4 6. G 4 5 4 H 4 5 6. J 12 K 7 8 8. 10 69

Step by Step Solution

3.43 Rating (153 Votes )

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Project Management

Authors: Jack Gido, Jim Clements

4th Edition

9780324656152, 324656130, 978-0324656138

More Books

Students also viewed these Management Leadership questions

Question

Discuss how the Internet can facilitate project communications.

Answered: 1 week ago