Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Draw PERT Chart with earliest and latest start and finish times/activity. Fill in the slack time in the table for each activity. Show the slack

  1. Draw PERT Chart with earliest and latest start and finish times/activity. Fill in the slack time in the table for each activity. Show the slack time for each path for all paths and show Critical Path (CP) and CP time.
  2. For the project duration, show staffing profile, beginning at the earliest time (forward pass) +Totals +Max Delta
  3. For the project duration, show staffing profile, beginning at the latest time (backward pass) +Totals+ Max Delta
  4. Suggest moving only one activity only to best level staffing requirements (from either Fwd or Bkd Pass). Make sure to give total staffing required and maximum (delta) reduction in staffing for the duration of the project.
  5. Which one activity only is best to crash to shorten project time in how many weeks (in some cases two activities might be required to crash). Show the results and the new Critical Path(s) if you crash the one activity

image text in transcribed
ID 5 Start End Activity Staff Crashing Activity Node Node Time Required Cost A S 1 800 B S 2 600 C S 3 6 900 D 1 5 6 3 1000 E 2 5 6 A 500 F 2 End 8 3 900 G 3 End 4 2 1000 H 5 End 7 4 1200

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Experiencing MIS

Authors: David Kroenke

3rd Edition

0132667169, 9780132667166

More Books

Students also viewed these General Management questions