Draw the network and identify the critical path. Calculate the earliest-latest starting and finishing times for each activity. Also, calculate Activity Slack times for each
Draw the network and identify the critical path. Calculate the earliest-latest starting and finishing times for each activity. Also, calculate Activity Slack times for each activity. Activity Preceding Activity Time in Weeks A 4 B 8 C 6 D A 6 E B 6 F B 8 G C 4 H D, E 7 F, G. H 3