Question
1 Approved Answer
Draw the network diagram and identify the critical path. Provide a table illustrating each activity, and the corresponding ES, EF, LS, LF, and Slack. Activity
- Draw the network diagram and identify the critical path. Provide a table illustrating each activity, and the corresponding ES, EF, LS, LF, and Slack.
Activity
Preceding Activity
Time (Weeks)
A
-
7
B
-
8
C
-
6
D
A
6
E
B
6
F
B
8
G
C
4
H
D,E
7
I
F,G,H
3
Activity | Preceding Activity | Time (Weeks) |
A | - | 7 |
B | - | 8 |
C | - | 6 |
D | A | 6 |
E | B | 6 |
F | B | 8 |
G | C | 4 |
H | D,E | 7 |
I | F,G,H | 3 |
2. Complete all ES, EF, LS, and LF information for the following network diagram (as shown in the image). Determine the critical path.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started