Draw the network diagram and identify the critical path. Provide a table illustrating each activity, and the corresponding ES, EF, LS, LF, and Slack. (12
- Draw the network diagram and identify the critical path. Provide a table illustrating each activity, and the corresponding ES, EF, LS, LF, and Slack.
(12 pts total: 9pts for the Activity table and 3pts - Critical Path)
Activity | Preceding Activity | Time (Weeks) |
A | - | 7 |
B | - | 8 |
C | - | 6 |
D | A | 6 |
E | B | 6 |
F | B | 8 |
G | C | 4 |
H | D,E | 7 |
I | F,G,H | 3 |
- Complete all ES, EF, LS, and LF information for the following network diagram. Determine the critical path. (14pts total: 11pts - 11 Activities and 3pts - Critical Path)
- For the network diagram illustrated above answer the following questions:
- What is the impact on the end date of the project if activity I slips by three weeks?
- By how many weeks can activity D slip before the end date gets extended?
- If activity A slips by one week, how will the slack in activity G be impacted?
- If activity H can somehow be compressed from seven weeks to two weeks, perhaps by adding a significant number of resources, what will the impact, if any, on the end date of the project? (4pts)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started