Question

1 Approved Answer

Draw the network for the project below. Do the CPM calculations based on the most likely durations. Pick the longest three paths. Calculate the Expected

Draw the network for the project below. Do the CPM calculations based on the most likely durations. Pick the longest three paths. Calculate the Expected Duration and Standard Deviation for each path. Considering all three paths, what is the duration of the project with at least 90% confidence?

image text in transcribed
Duration (Days) Activity IPA Optimistic (To) Most Likely (Tm) Pessimistic (Tp) 11 6 15 A. B 11 B 10 NWONDOWOWA D 8 D. E 16 C. F. G 10 C. G H

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Hospitality Management

Authors: John R Walker

3rd Edition

0135061385, 9780135061381

More Books

Students also viewed these General Management questions

Question

Describe ERP and how it can create efficiency within a business

Answered: 1 week ago