Dubai Municipality prepares an annual budget for its infrastructure projects. The budgeted and actual expenses for the construction of a new park are as follows:
Dubai Municipality prepares an annual budget for its infrastructure projects. The budgeted and actual expenses for the construction of a new park are as follows:
- Budgeted Expenses: AED 10,000,000
- Actual Expenses: AED 12,500,000
Compute the budget variance, favorable or unfavorable, for Dubai Municipality's park construction project. Analyze the possible reasons for the variance and recommend actions to address it.