Question: Dummy activities are used when two activities have identical starting and ending events all of the above are inserted into networks to maintain the logic

Dummy activities
are used when two activities have identical starting and ending events
all of the above
are inserted into networks to maintain the logic of the network
have no time
 Dummy activities are used when two activities have identical starting and