Question

1 Approved Answer

Duration of activity(days) A 4 Duration of activity(days) B 15 Duration of activity(days) C 10 Duration of activity(days) D 8 Duration of activity(days) E 5

Duration of activity(days) A 4
Duration of activity(days) B 15
Duration of activity(days) C 10
Duration of activity(days) D 8
Duration of activity(days) E 5
Duration of activity(days) F 3
image text in transcribed Q2 (20 points): The activity information table and calendar of a construction project, which will start on the 1-January-2024, are given below. Using this information, answer the following questions: : Nonworking days a) (4 pts.) Draw the Activity-on-Node (A-o-N) diagram of the project. b) (4 pts.) Carry out the CPM calculations (forward pass \& backward pass) on the network to find the critical path of the project. c) (4 pts.) Find the completion date of the project. d) (4 pts.) Find the total project duration in terms of working days. e) (4 pts.) Find the total float of Activity A

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions