During 2 0 2 0 , Flint Corporation started a construction job with a contract price of $ 3 . 3 6 million. Flint ran

During 2020, Flint Corporation started a construction job with a contract price of $3.36 million. Flint ran into severe technical difficulties during construction but managed to complete the job in 2022. The contract is non-cancellable. Under the terms of the contract, Flint sends billings as revenues are earned. Billings are non-refundable. The following information is available:
20202021
2022
Costs incurred to date
$ 480,000 $1,680,000 $3,260,000
Estimated costs to complete
2,520,0001,680,000-0-
(a)
Calculate the amount of gross profit that should be recognized each year under the percentage-of-completion method. (Enter negative amounts using either a negative sign preceding the number e.g.-45 or parentheses e.g.(45).)
202020212022
Gross profit /(loss) $enter a dollar amount
$enter a dollar amount
$enter a dollar amount
eTextbook and Media
List of Accounts
Attempts: 0 of 2 used
(b1)
The parts of this question must be completed in order. This part will be available when you complete the part above.
(c1)
The parts of this question must be completed in order. This part will be available when you complete the part above.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Routledge Handbook Of Environmental Accounting

Authors: Jan Bebbington, Carlos Larrinaga, Brendan O'Dwyer, Ian Thomson

1st Edition

0367724901, 9780367724900

More Books

Students also viewed these Accounting questions