During 2 0 2 0 , Monty Company started a construction job with a contract price of $ 1 , 6 2 0 , 0

During 2020, Monty Company started a construction job with a contract price of $1,620,000. The job was completed inDuring 2020, Monty Company started a construction job with a contract price of $1,620,000. The job was completed in
The following information is available.
(a)
Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is
used.
Gross profit recognized in 2020$
Gross profit recognized in 2021$
Gross profit recognized in 2022$
2022. The following information is available.
Costs incurred to date
Estimated costs to complete
Billings to date
Collections to date
2020
$444,400
565,600
301.000
272.000
2021
$867,420
230.580
904.000
814.000
2022
$1,060,000
-0-
1.620.000
1,411,000
(a)
Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.
Gross profit recognized in 2020
Gross profit recognized in 2021
Gross profit recognized in 2022
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions

Question

Determine miller indices of plane X z 2/3 90% a/3

Answered: 1 week ago