Question
1 Approved Answer
During 2007, Eaton. Corp. started a construction job with a total contract price of $3,500,000. The job was completed on December 15, 2008. Additional data
During 2007, Eaton. Corp. started a construction job with a total contract price of $3,500,000. The job was completed on December 15, 2008. Additional data are as follows:
2007 2008
Actual Costs incurred: $1,350,000 $1,525,000
Estimated Remaining costs: 1,350,000 -----
Billed to customer: 1,200,000 2,300,000
Received from customer: 1,000,000 2,400,000
Under the completed-contract method, what amount should Eaton recgonize as gross profit for 2008?
a. $225,000
b. $312,500
c. $475,000
d. $625,000
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started