During 2010 Majan Company started a construction job with a contract price of $1,600,000. The job was completed in 2012. The following information is available.
- During 2010 Majan Company started a construction job with a contract price of $1,600,000. The job was completed in 2012. The following information is available.
| 2010 | 2011 | 2012 |
Cost incurred to date | $400,000 | $825,000 | $1,070,000 |
Estimated costs to complete | 600,000 | 275,000 | 0 |
Billings to date | 300,000 | 900,000 | 1,600,000 |
Collections to date | 270,000 | 810,000 | 1,425,000 |
Instructions: Compute the amount of gross profit to be recognized each year assuming the percentage-of-completion method is used.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started