During 2010 Majan Company started a construction job with a contract price of $1,600,000. The job was completed in 2012. The following information is available.

  1. During 2010 Majan Company started a construction job with a contract price of $1,600,000. The job was completed in 2012. The following information is available.

2010

2011

2012

Cost incurred to date

$400,000

$825,000

$1,070,000

Estimated costs to complete

600,000

275,000

0

Billings to date

300,000

900,000

1,600,000

Collections to date

270,000

810,000

1,425,000

Instructions: Compute the amount of gross profit to be recognized each year assuming the percentage-of-completion method is used.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Commercial Energy Auditing Referance Handbook

Authors: Steve Doty

1st Edition

0881736481, 978-0881736489

More Books

Students also viewed these Accounting questions