During 2014, Nilsen Company started a construction job with a contract price of $1,706,000. The job was completed in 2016. The following information is available.
During 2014, Nilsen Company started a construction job with a contract price of $1,706,000. The job was completed in 2016. The following information is available.
2014 | 2015 | 2016 | |
Costs incurred to date | $344,400 | $887,170 | $1,098,000 |
Estimated costs to complete | 639,600 | 235,830 | 0 |
Billings to date | 281,000 | 883,500 | 1,706,000 |
Collections to date | 269,300 | 823,400 | 1,446,000
Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started