During 2014, Nilsen Company started a construction job with a contract price of $1,706,000. The job was completed in 2016. The following information is available.

During 2014, Nilsen Company started a construction job with a contract price of $1,706,000. The job was completed in 2016. The following information is available.

2014 2015 2016
Costs incurred to date $344,400 $887,170 $1,098,000
Estimated costs to complete 639,600 235,830 0
Billings to date 281,000 883,500 1,706,000
Collections to date 269,300 823,400

1,446,000

Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Cost Accounting

Authors: William N. Lanen, Shannon Anderson, Michael W Maher

6th edition

1259969479, 1259565408, 978-1259969478

More Books

Students also viewed these Accounting questions