Question
1 Approved Answer
during 2014 nilsen company started a construction job with a contract price of 2,000,000.The job was completed in 2016. The following information is available. 2014.
during 2014 nilsen company started a construction job with a contract price of 2,000,000.The job was completed in 2016. The following information is available. 2014. 2015. 2016 Cost 300,000. 825,000. 1,070,000 incurred estimated costs to complete. 700,000. 275,000. 0 billing to date. 300,000. 900,000. 2,000,000 collections to date. 270,000. 810,000. 1,425,000
Required compute the amount of revenue and gross profit to be recognized each year using 1. Revenue over time method (percentage of completion method)
2. Completed contract method
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started