Question
During 2016, the Samuelson Construction Company began construction on an office building for the City of Gernon. The contract price is $8,000,000 and the building
During 2016, the Samuelson Construction Company began construction on an office building for the City of Gernon. The contract price is $8,000,000 and the building will take approximately 18 months to complete. Completion is scheduled for early in 2018. The companys fiscal year ends on December 31.
The following is a year-by-year recap of construction costs incurred and the estimated costs to complete the project as of the end of each year. Progress billings and cash collections also are indicated.
| 2016 | 2017 | 2018 |
Actual costs incurred during the year | $1,500,000 | $4,500,000 | $1,550,000 |
Actual costs incurred in prior years | 0 | 1,500,000 | 6,000,000 |
Cumulative actual costs incurred to date | 1,500,000 | 6,000,000 | 7,550,000 |
Estimated costs to complete at end of year |
4,500,000 |
1,500,000 |
0 |
Total costs (actual + estimated) | $6,000,000 | $7,500,000 | $7,550,000 |
Billings made during the year |
$1,400,000 |
$5,200,000 |
$1,400,000 |
Cash collections during year | 1,000,000 | 4,000,000 | 3,000,000 |
PART B: Assume the contract does NOT quality for recognizing revenue over time.
How much revenue will be recognized in each of the years?
Prepare the necessary revenue related journal entries that would be recorded for revenue recognition in each of the years. (If no entry, note no entry.)
Prepare the balance sheet related journal entries for each of the years.
What amount would be recorded as the contract asset or liability at the end of each of the years?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started