Question

1 Approved Answer

During 2018 ESAU Construction began work on a project 2018-03B for a contract price of $12.8m. ESAU incurred costs of $4m in 2018 and estimated

During 2018 ESAU Construction began work on a project 2018-03B for a contract price of $12.8m. ESAU incurred costs of $4m in 2018 and estimated at the end of the year that the remaining costs to complete the job would be $5.5m. During 2019 the company expended $3.0m and at year-end estimated that an additional $3.5m of costs would be incurred in 2020 to finish the project.

Assuming that ESAU books $3.0m of expenses for this project in 2019, provide the journal entry to recognize revenue in 2019 using the percentage of completion method.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Entrepreneurial Financial Management An Applied Approach

Authors: Jeffrey R. Cornwall, David O. Vang, Jean M. Hartman

4th Edition

0765646854, 978-0765646859

More Books

Students also viewed these Accounting questions

Question

what is P/E ratio?

Answered: 1 week ago