During 2020 AFCO started a construction job with a contract price of $2,500,000. The job was completed in 2022. The following information is available: 2020
During 2020 AFCO started a construction job with a contract price of $2,500,000. The job was completed in 2022.
The following information is available:
2020 2021 2022
Costs incurred to date 600,000 1,435,000 2,100,000
Estimated costs to complete 1,400,000 615,000 0 ZERO
Billings to date 100,000 500,000 2,500,000
Collections to date 100,000 300,000 2,000,000
Instructions
(a) Compute the amount of gross profit to be recognized each year assuming the percentage-of completion method is used.
(b) Prepare all necessary journal entries for 2021.
(c) Compute the amount of gross profit to be recognized each year, assuming the completed-contract method is used.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started