Question

1 Approved Answer

During 2020, Bing Corp. started a construction job with a total contract price of $1,050,000. Bing has consistently used the completed contract method. The job

During 2020, Bing Corp. started a construction job with a total contract price of $1,050,000. Bing has consistently used the completed contract method. The job was completed on December 15, 2021. Additional data are as follows:

2020

2021

Actual costs incurred

$405,000

$457,000

Estimated remaining costs

405,000

Billings to date

360,000

690,000

Collections to date

200,000

480,000

For 2020, what amount should Bing recognize as gross profit?

$120,000

$142,500

$187,500

$0

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Bookkeeping And Accounting

Authors: Greg Shields

1st Edition

1983673536, 978-1983673535

More Books

Students also viewed these Accounting questions

Question

Detailed note on the contributions of F.W.Taylor

Answered: 1 week ago

Question

Discuss how selfesteem is developed.

Answered: 1 week ago