During 2020, Blue Spruce Corporation started a construction job with a contract price of $6.16 million. Blue Spruce ran into severe technical difficulties during construction

During 2020, Blue Spruce Corporation started a construction job with a contract price of $6.16 million. Blue Spruce ran into severe technical difficulties during construction but managed to complete the job in 2022. The contract is non-cancellable. Under the terms of the contract, Blue Spruce sends billings as revenues are earned. Billings are non-refundable. The following information is available:

2020 2021 2022
Costs incurred to date $ 880,000 $3,080,000 $6,060,000
Estimated costs to complete 4,620,000 3,080,000 -0-

Calculate the amount of gross profit that should be recognized each year under the percentage-of-completion method.

2020

2021

2022

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Forensic Analytics Methods And Techniques For Forensic Accounting Investigations

Authors: Mark J. Nigrini

2nd Edition

1119585767, 9781119585763

More Books

Students also viewed these Accounting questions

Question

Can knowledge workers and/or professionals be performance-managed?

Answered: 1 week ago

Question

Does a PMS enhance strategic integration within HRM?

Answered: 1 week ago