During 2020, Crane Company started a construction job with a contract price of $1,216,000. The job was completed in 2022. The following information is available.
During 2020, Crane Company started a construction job with a contract price of $1,216,000. The job was completed in 2022. The following information is available. The contract is non-cancellable.
2020 | 2021 | 2022 | ||||
---|---|---|---|---|---|---|
Costs incurred to date | $304,000 | $627,000 | $813,200 | |||
Estimated costs to complete | 456,000 | 209,000 | 0 | |||
Billings to date (non-refundable) | 228,000 | 684,000 | 1,216,000 | |||
Collections to date | 205,200 | 615,600 | 1,083,000 |
(a)
Calculate the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. (Enter negative amounts using either a negative sign preceding the numbe
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started