Question

1 Approved Answer

During 2020, Indigo Corporation started a construction job with a contract price of $5.46 million. Indigo ran into severe technical difficulties during construction but managed

During 2020, Indigo Corporation started a construction job with a contract price of $5.46 million. Indigo ran into severe technical difficulties during construction but managed to complete the job in 2022. The contract is non-cancellable. Under the terms of the contract, Indigo sends billings as revenues are earned. Billings are non-refundable. The following information is available:

Cost Incurred to Date:

2020: 780,000

2021: 2730,000

2022: 5360,000

Estimated costs to complete:

2020: 4095,000

2021: 2730,000

2022: 0 (Zero)

REQUIRED:

Calculate the amount of gross profit that should be recognized each year under the percentage-of-completion method.(Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Accounting In A Dynamic Environment

Authors: Cheryl S McWatters, Jerold L Zimmerman

1st Edition

0415839025, 9780415839020

More Books

Students also viewed these Accounting questions

Question

Define Administration and Management

Answered: 1 week ago

Question

Define organisational structure

Answered: 1 week ago