Question
During 2020, Nilsen Company started a construction job with a contract price of $1.6 million. The job was completed in 2022. The following information is
During 2020, Nilsen Company started a construction job with a contract price of $1.6 million. The job was completed in 2022. The following information is available. The contract is non-cancellable.
| 2020 | 2021 | 2022 |
---|---|---|---|
Costs incurred to date | $400,000 | $825,000 | $1,070,000 |
Estimated costs to complete | 600,000 | 275,000 | -0- |
Billings to date (non-refundable) | 300,000 | 900,000 | 1,600,000 |
Collections to date | 270,000 | 810,000 | 1,425,000 |
Instructions
a.
Calculate the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.
b.
Prepare all necessary journal entries for 2021.
c.
Calculate the amount of gross profit to be recognized each year, assuming the completed-contract method is used.
use the following table to complete this question:
|
|
|
|
| 2017 | 2018 | 2019 |
CONTYRACT PRICE |
|
|
|
COSTS: |
|
|
|
OPENING BALNACE OF COSTS |
|
|
|
COSTS INCURRED DURING THE YEAR |
|
|
|
COSTS TODATE |
|
|
|
ESTIMATED COSTS TO COMPLETE |
|
|
|
ESTIMATED TOTAL COSTS |
|
|
|
|
|
|
|
PERCENT COMPLETE |
|
|
|
|
|
|
|
REVENUE TODATE |
|
|
|
LESS: REVENUE RECOGNIZED PREVIOUSLY |
|
|
|
REVENUE FOR THE YEAR |
|
|
|
|
|
|
|
CONSTRUCTION COSTS FOR THE YEAR |
|
|
|
|
|
|
|
PROFITS FOR THE YEAR |
|
|
|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started