Answered step by step
Verified Expert Solution
Link Copied!

Question

...
1 Approved Answer

During 2020, Pharoah Company started a construction job with a contract price of $1,620,000. The job was completed in 2022. The following information is available.

During 2020, Pharoah Company started a construction job with a contract price of $1,620,000. The job was completed in 2022. The following information is available.

2020

2021

2022

Costs incurred to date

$373,700 $902,000 $1,070,000

Estimated costs to complete

636,300 198,000 0

Billings to date

303,000 899,000 1,620,000

Collections to date

273,000 807,000 1,412,000

Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.

Gross profit recognized in 2020

$enter a dollar amountenter a dollar amount

image text in transcribed

Gross profit recognized in 2021

$enter a dollar amountenter a dollar amount

image text in transcribed

Gross profit recognized in 2022

$enter a dollar amountenter a dollar amount

image text in transcribed

Prepare the journal entries to record profit or loss, if any using the percentage-of completion-method and (B) the completed- contract method

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials Of Federal Taxation 2018

Authors: Brian Spilker, Benjamin Ayers, John Robinson, Edmund Outslay, Ronald Worsham, John Barrick, Connie Weaver

9th Edition

9781260007640

Students also viewed these Accounting questions