Answered step by step
Verified Expert Solution
Question
1 Approved Answer
During 2020, Sheridan Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available.
During 2020, Sheridan Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available.
2020 | 2021 | 2022 | ||||
---|---|---|---|---|---|---|
Costs incurred to date | $396,000 | $806,600 | $1,080,000 | |||
Estimated costs to complete | 594,000 | 283,400 | 0 | |||
Billings to date | 301,000 | 892,000 | 1,590,000 | |||
Collections to date | 268,000 | 816,000 | 1,427,000 |
Compute the amount of gross profit to be recognized each year, assuming the completed-contract method is used.
2020 | 2021 | 2022 | ||||
---|---|---|---|---|---|---|
Gross profit | $enter a dollar amount | $enter a dollar amount | $enter a dollar amount |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started