During 2020, Sunland Company started a construction job with a contract price of $1,408,000. The job was completed in 2022. The following information is available.

During 2020, Sunland Company started a construction job with a contract price of $1,408,000. The job was completed in 2022. The following information is available. The contract is non-cancellable.

2020 2021 2022

Costs incurred to date

$352,000 $726,000 $941,600

Estimated costs to complete

528,000 242,000 0

Billings to date (non-refundable)

264,000 792,000 1,408,000

Collections to date

237,600 712,800 1,254,000

QUESTION:

A) Calculate the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.

B) Prepare all necessary journal entries for 2021. (Use Materials, Cash, Payables for costs incurred to date.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing The Art And Science Of Assurance Engagements

Authors: Alvin A. Arens, Randal J. Elder, Mark S. Beasley, Ingrid B. Splettstoesser-Hogeterp

11th Edition

0132088061, 978-0132088060

More Books

Students also viewed these Accounting questions

Question

What would I do next and why?

Answered: 1 week ago

Question

Roll out international HRM practices for franchisees.

Answered: 1 week ago