Question
During 2020, Teal Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available.
During 2020, Teal Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $393,900 $760,380 $1,059,000 Estimated costs to complete 616,100 341,620 0 Billings to date 299,000 905,000 1,610,000 Collections to date 268,000 818,000 1,421,000
(a) Correct answer icon Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount 234000 Gross profit recognized in 2021 $enter a dollar amount 116520 Gross profit recognized in 2022
(b) Prepare all necessary journal entries for 2021.
(c)Compute the amount of gross profit to be recognized each year, assuming the completed-contract method is used.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started